Commercial waterfront work follows a heavier permit path than a home dock, and the general permits that speed up homeowners exclude new marinas.
What does a storm do to a marina in this area?
Sally showed the pattern in 2020. Surge damage was worst in the back bays and sounds, where large boats were moved onto land and many docks and piers were destroyed. NHC Sally report At Fort Morgan, a marina boat storage building took major damage. NWS Mobile Sally report
Nate in 2017 damaged just under 200 piers in Baldwin County. NWS Mobile Nate report
Plan recovery work before the season starts. A damaged structure can be rebuilt under Corps Nationwide Permit 3 if work starts or is under contract within two years. Corps NWP 3
Which design limits apply to commercial docks?
State Lands limits structures on state submerged lands to 25 percent of the waterbody width at that location. It also keeps them at least 100 feet from a federal channel. ADCNR rule 220-4-.09
The Corps general permit for piers caps terminal structures at 3,000 square feet and three berthing areas per site. Corps ALGP-05 ADEM then bars that permit for habitable structures, fueling, new marinas and marina expansions. ADEM coastal conditions
- Keep platforms, T's and L's at the waterward end.
- Keep structures off wetlands and seagrass. ADEM and Corps rules
Which approvals does a marina need?
In Orange Beach, a marina goes through the Planned Unit Development process, must address wetlands, navigation and pollution, and must hold its Corps and other agency permits. Live-aboards must connect to sewer. Orange Beach Zoning Ordinance 10.04
Work not covered by a general permit goes to a Letter of Permission or a standard permit with a 30-day public notice. Corps Mobile District The Corps charges $100 for a commercial individual permit. 33 CFR 325.1(f)
- ADEM fee for other pile-supported piers or docks: $2,400. ADEM Fee Schedule B
- State Lands: a Consent of Use covers docks for one or two single-family parcels. ADCNR rule 220-4-.09 Structures that do not qualify pay an annual riparian easement fee, with a $775 minimum as of July 15, 2022. ADCNR easement fees
Common questions
Can a marina use the Corps general permit for piers?
Not for new marinas or expansions in the coastal area. ADEM conditions bar that use. ADEM coastal conditions
Who do I call first?
Start with the city or county permit office, then the Corps at (251) 690-2658 and State Lands at (251) 621-1216. Corps Mobile District ADCNR Coastal Section
Does a commercial bulkhead need a license check?
Yes. Marine construction and retaining walls are General Contractors Board classifications, and work of $100,000 or more needs that license. General Contractors Board rule 230-X-1-.27 Code of Alabama 34-8-1
Are fuel docks or live-aboards allowed under the general permit?
Not under the pier general permit, which bars fueling and habitable structures in the coastal area. ADEM coastal conditions
How early should we file for a repair?
The Corps recommends general permit notices at least 60 days before work. Corps ALGP package
What happens after a hurricane?
The district engineer may extend the two-year repair window if you show funding or contract delays. Corps NWP 3
What clocks start after storm damage?
The Corps maintenance permit covers storm-damaged structures if work starts or is under contract within two years, and hurricanes can earn an extension. Corps NWP 3
State Lands treats a structure as substantially rebuilt when more than half of it changes or any piling is altered. ADCNR rule 220-4-.09(2)
ADEM can approve emergency actions without prior notice for up to 120 days. ADEM rule 335-8-1-.07
What do public bids show about price swings?
Public bids give real spreads. Baldwin County's 2022 Lillian boat launch bids for vinyl sheet pile wall ran from about $256 to $611 per linear foot. Baldwin County bid WG23-03
A 2018 county timber bulkhead job drew bids of $419, $585 and $725 per linear foot. Baldwin County project BCP 0206816
Compare scopes before prices. Different bidders price different details.
How do we plan the return to service?
Orange Beach's marina rule requires every required agency permit before approval. Orange Beach Zoning Ordinance 10.04 The Corps asks for a start and finish notice and a posted authorization card on site. Corps Alabama general permits
- Stage berths so slips reopen as sections finish.
- Tell tenants the dates in writing.
- Keep lien releases from each contractor tier.
Show sourcesHide sources
- 2026 Nationwide Permit 3, Maintenance, 91 FR 768Source reviewed 2026-10-31
- ADCNR Admin. Code r. 220-4-.09 Placement and Configuration of Piers and Other Improvements on State Owned Submerged LandsSource reviewed 2026-10-31
- ADEM Admin. Code Chapter 335-8-1, rule 335-8-1-.07 General ConditionsSource reviewed 2026-10-31
- WG23-03 - Certified Bid Tabulation, Lillian Boat Launch (Sawgrass bid tabulation, October 2022)Source reviewed 2026-10-31
- Seminole Landing Boat Launch - Bid Tabulation (BCP 0206816)Source reviewed 2026-10-31
- City of Orange Beach Zoning Ordinance No. 172, amended through May 6, 2025Source reviewed 2026-10-31
- 2026 Alabama General Permit Program, General Conditions GC-10 to GC-14Source reviewed 2026-10-31
Discuss a waterfront business project
Record the affected shoreline and the decision you need to make. Use the notes when discussing scope with the appropriate professional.